NV5 - Liquefaction Pretreatment System Upgrade

Liquefaction Pretreatment System Upgrade

Due to increased CO2 composition in the feed gas, this facility was only able to liquefy at about 65% of its designed capacity. NV5 upgraded the pretreatment system to increase C02 removal capacity from a 1% Co2 to 2% C02 feed gas. This upgrade allowed the facility to achieve full liquefaction capacity of 20 MMSCFD.

 

Facebooktwitterlinkedin

Services

EPC Services

Key Facts

Capacity 20 MSMSCFD