Oracle, Conditions Assessment, 4,6,8 & 10 Van de Graaff Drive, 1, 35 & 95 Network Drive

NV5 provided facility site assessments for Oracle at 4, 6, 8, and 10 Van de Graaf Drive, and 1, 35, and 95 Network Drive in Burlington, MA. The goal of this effort was to conduct a facility assessment and develop a road map to outline proposed mitigation efforts to prevent the likelihood of system failures and business interruptions.

HVAC Systems evaluated by NV5 include: Boilers/Hot Water Tanks, Control Zone Valves, Heat Exchangers, Packaged Pumping, Primary & Secondary Pumping, RTUS/AHUS/MAUS/Fans, Terminal Devices, Walk-in Cooler/Freezers, Plumbing, Domestic Water Recirculation Pumps, Domestic Water Booster Pumps, Pressure Reducing Valve Stations and Gauges, Thermostatic Mixing Valves, Water Heaters and Tanks.

Electrical, Vertical Transportation, Building Envelope and Fire Alarm/Life Safety systems evaluated by NV5 include: Arch Flash Studies, Electrical Distribution Panels, Electrical Room Transformers, Medium-voltage Equipment, UPS, Variable Frequency Drives, Passenger Elevators/Escalators Equipment, Controls, Building Automation, Exterior Walls, Fenestrations, Roofs, and review of firm alarm system.

Location

Burlington, MA

Client

ORACLE America, INC.

Services

Key Facts

  • Project Size: 830,765 SF (COMBINED TOTAL OF SEVEN BUILDINGS)
  • Construction Cost: N/A
  • Project Timeline: 2019-2022