Projects

Former Power Plant Remediation & Demolition

The former power plant at the University of Massachusetts-Amherst campus was a coal- and oil-fired plant that was rendered obsolete with the completion of the school’s new central heating plant. The old 43,900 SF power plant facility first was remediated of asbestos-containing materials and PCBs, then demolished.

NV5 was retained as the Owner’s Project Manager and provided all technical and management expertise for the remediation and demolition of the former power plant. This included monitoring the procurement process, and all schedules and budgets, along with overseeing compliance with contract documents.


Facebooktwitterlinkedin

Location

Amherst, MA

Services

Owner’s Representation Services

Key Facts

  • 43,900 SF
  • Project Cost $10.9M