NV5 was retained as the Owner’s Scheduling Consultant for a six phase build-out.

Phase 1 included a full renovation of the outpatient entrance, lobby, gift shop, and chapel. Phase 2 consisted of two major building additions including new PED’s, surgery recovery, and a new main visitor lobby. Phases 3 through 6 included adding  three operating rooms, renovation of surgery support areas and storage rooms, renovation of respiratory therapy, radiology including relocation of nuclear medicine, both first and second floor main corridors, labs, and SDS.

Facebooktwitterlinkedin

Location

Westlake, OH

Services

  • Project Controls
  • Scheduling

Key Facts

  • 146,000 SF
  • Project Cost $53M